Road closures, road works, maintenance or temporary restrictions in Porirua

Keep up to date with any road closures, temporary restrictions, or disruptions within Porirua city.

Current road closures, road works, temporary restrictions, and disruptions in Porirua

Updated on 12 May 2025

There are times when emergency events, repairs or largescale improvement projects force the closure or disruption of roads in Porirua. Sometimes for a number of weeks, or longer.

We appreciate this is disruptive for residents and do our best to reopen roads as soon as it is safe to do so.

To see what road works, road closures or disruptions are currently active, click on the suburbs below.

If you want to know what work is currently happening on SH58 and SH59 within Porirua here is a link to the NZTA website.


Ascot Park


Aotea


Camborne


Cannons Creek

In the week beginning 14 April, we'll be carrying out road repairs on Hampshire Street and Sievers Grove. Traffic management will be in place, so there may be some delays.

While the work is planned for this date, it can be delayed due to weather or unforeseen circumstances. Work will be completed on the next suitable day.

We appreciate your co-operation and patience.

Hampshire St and Sievers Grove

The car park outside 14 Bedford Court, Te Akapuanga Hall (Porirua Cook Islands Hall), will be closed between midday and 10pm on the following days for the Pacific Night Market:

Friday 30 May

Friday 27 June

City Centre


Elsdon

Electricity cabling - October to April 2025
Wellington Electricity is installing an underground electricity cable between 11 Prosser Street and 24 Mohuia Crescent in Elsdon, Porirua. The project involves digging trenches, installing protective pipes, then covering everything up once the cables are in place. The duct installation is complete and some excavation work is still being done. The work is expected to be completed late March/early April.

For up-to-date information about what is happening and when, visit the Wellington Electricity project page: https://www.welectricity.co.nz/major-projects/elsdon/

From 12 May we're carrying out road works to Sievers Grove. Traffic management will be in place, so please plan for minor delays.

Thank you for your patience while this work is carried out.

Water main installation - January 2025 to July 2025

Wellington Water is working to install a new water main on Titahi Bay Road (near Wi Neera Drive) and along Tangare Drive.

It is being carried out in stages and is a joint effort between Wellington Pipelines and Wellington Water.

Stage 1 construction has now been completed. Final close out activities are happening and Stage 2 has been deferred to July 2025.

Please note, the depot will remain in place until completion of the project in 2025.


Judgeford

Week beginning 5 May, we'll be in Belmont Road carrying out road cleaning work. A two way stop/go will in place, and this may result in minor delays.

Thank you for your patience while this work is carried out.

Week beginning 5 May, we'll be in Murphys Road carrying out road cleaning work. A two way stop/go will in place, and this may result in minor delays.

Thank you for your patience while this work is carried out.


Kenepuru


Papakōwhai

A slip in 2022 has resulted in the long-term closure of the walkway between Halladale Road and Kinloch Grove.

The retaining works required will be programmed as priorities and budget allow.

There is currently no timeframe for these works - and the walkway will remain closed until it can be safely reopened.

We recognise this closure will be frustrating for many residents.


Paremata / Mana


Pāuatahanui

From Monday 19 May we will be undertaking work on Paekākāriki Hill Road between numbers 483 and 504 to restabilise the road and the Horokiri stream bank. This will take up to four weeks to complete.

One lane will be closed with stop/go traffic management and a 30km/hr speed limit will be in place for the duration of the work. Hours of work are expected to be 7:30am–6pm weekdays.

Thank you for your cooperation and patience while this important work is carried out.


Plimmerton

In the week of 12 May we will be carrying out works near 70 Cluny Road. Traffic management will be in place, so please plan for minor delays.

Thank you for your patience while this work is carried out.


Pukerua Bay


Rānui

Sewer main renewal – 24 July to February 2025

Windley Street will be closed at the intersection of Windley Street and Champion Street. Kāinga Ora, will be carrying out a wastewater renewal project during this road closure.

There will be a full road closure of Windley Street, between Thompson Grove and Champion Street. Traffic will be managed under a Stop Go operation.

The businesses will remain open and accessible.


Titahi Bay

Water main installation - January 2025 to July 2025

Wellington Water is working to install a new water main on Titahi Bay Road (near Wi Neera Drive) and along Tangare Drive.

It is being carried out in stages and is a joint effort between Wellington Pipelines and Wellington Water.

Stage 1 construction has now been completed. Final close out activities are happening and Stage 2 has been deferred to July 2025.

Please note, the depot will remain in place until completion of the project in 2025.


Waitangirua


Whitby

Lane closed from Transmission Gully into Whitby in the week starting Tuesday 22 April
The lane into Whitby from Transmission Gully is closed for approximately two months to allow for water pipes and electricity cabling to be laid. Motorists can exit Whitby using Te Ara Kāpehu but not enter on this road, which is closed between the T-junction with Waitangirua Link Road and the Silverbrooke development. A 30km/h temporary speed limit is in place during the work. Motorists are advised to allow extra time and use alternative routes.
For more information visit the Link Road page

Spinnaker Drive slip and road closure updates can be found here: poriruacity.govt.nz/spinnaker



Traffic advice

  • Well-maintained roads are an important part of keeping people safe. While we aim to do this work with as little disruption as possible, we know that roadworks can be inconvenient. 
  • Please drive carefully through work sites and stick to the temporary speed limits. 
  • If you’re driving around the Wellington region, roadworks on the state highway network may affect your travel plans.
  • Please contact us on (04) 237 5089, email [email protected], or use the Antenno app to report any concerns you might have.