Updated on 4 April 2025
There are times when emergency events, repairs or largescale improvement projects force the closure or disruption of roads in Porirua. Sometimes for a number of weeks, or longer.
We appreciate this is disruptive for residents and do our best to reopen roads as soon as it is safe to do so.
To see what road works, road closures or disruptions are currently active, click on the suburbs below.
If you want to know what work is currently happening on state highways within Porirua City, here is a link to the NZTA Waka Kotahi website.
Sewer main construction & water main renewal
Both lanes of Champion St are now open, however the entrance to Bothamley Park remains closed until further notice.
The car park outside 14 Bedford Court, Te Akapuanga Hall (Porirua Cook Islands Hall), will be closed between midday and 10pm on the following days for the Pacific Night Market:
Friday 30 May
Friday 27 June
On Friday 04 April, there will be traffic management in place at the corner of Lyttelton Avenue and Titahi Bay between 9am and 3pm to remove a sign pole, so please plan for potential delays in the area.
While the work is planned for this date, it can be delayed due to weather or unforeseen circumstances. Work will be completed on the next suitable day.
Approximate work site shown in in red below.
Electricity cabling - October to April 2025
Wellington Electricity is installing an underground electricity cable between 11 Prosser Street and 24 Mohuia Crescent in Elsdon, Porirua. The project involves digging trenches, installing protective pipes, then covering everything up once the cables are in place. The duct installation is complete and some excavation work is still being done. The work is expected to be completed late March/early April.
For up-to-date information about what is happening and when, visit the Wellington Electricity project page: https://www.welectricity.co.nz/major-projects/elsdon/
Water main installation - January 2025 to July 2025
Wellington Water is working to install a new water main on Titahi Bay Road (near Wi Neera Drive) and along Tangare Drive.
It is being carried out in stages and is a joint effort between Wellington Pipelines and Wellington Water.
Stage 1 construction has now been completed. Final close out activities are happening and Stage 2 has been deferred to July 2025.
Please note, the depot will remain in place until completion of the project in 2025.
A slip in 2022 has resulted in the long-term closure of the walkway between Halladale Road & Kinloch Grove.
The retaining works required will be programmed as priorities and budget allow.
There is currently no timeframe for these works - and the walkway will remain closed until it can be safely reopened.
We recognise this closure will be frustrating for many residents.
We are carrying out tree removals opposite 169 Paekākāriki Hill Road from Monday 31 March.
The work is expected to take five days, weather permitting, and stop/go traffic management will be installed each day from 9am and removed by 3pm. A stop/go will be in place at the north end of Jones Deviation.
Road users may experience some delays, and we thank you for your patience in advance while we carry out this important work.
Mepham Place will be closed for five (5) days between Friday 28 March and Friday 11 April 2025 for post construction road reinstatement. The road will be closed between the hours of 7am and 5pm.
While the work is planned for this date, it can be delayed due to weather or unforeseen circumstances. Work will be completed on the next suitable day.
We apologise for any inconvenience this may cause.
Thompson Grove will be closed for two (2) weeks from Monday 17 March until Thursday 3 April 2025 and allows for a five (5) day contingency period. This is an extension to a previous closure and is to reinstate the asphalt.
The road will be closed weekdays between the hours of 7am to 4pm and on Saturdays between the hours of 9am to 3pm. We apologise for any inconvenience this may cause.
While the work is planned for this date, it can be delayed due to weather or unforeseen circumstances. Work will be completed on the next suitable day.
Sewer main renewal – 24 July to February 2025
Windley Street will be closed at the intersection of Windley Street and Champion Street. Kāinga Ora, will be carrying out a wastewater renewal project during this road closure.
There will be a full road closure of Windley Street, between Thompson Grove and Champion Street. Traffic will be managed under a Stop Go operation.
The businesses will remain open and accessible.
A contractor for Wellington Electricity is carrying out work for a cable upgrade from Monday 4 November for approximately 8 weeks. Stop/Go traffic management and/or road shoulder closures will be in place. The footpath will remain open to pedestrians.
We understand roadworks can be disruptive and Wellington Electricity’s contractor will endeavour to minimise the impact on the community. We appreciate your co-operation and patience.
Water main installation - January 2025 to July 2025
Wellington Water is working to install a new water main on Titahi Bay Road (near Wi Neera Drive) and along Tangare Drive.
It is being carried out in stages and is a joint effort between Wellington Pipelines and Wellington Water.
Stage 1 construction has now been completed. Final close out activities are happening and Stage 2 has been deferred to July 2025.
Please note, the depot will remain in place until completion of the project in 2025.
On Saturday 5 April, Toms Road will be closed from 8am–2pm, with traffic management set up from 7am and reduced speeds in place.
A road closure will be in place on Monday 7 April between 9am–3pm to allow us to remove the chipseal on Trevor Terrace.
Residents may experience delays while entering or exiting their property, and we thank you for your patience.
Work to repave this road will be carried out in the following weeks. We will be in touch with residents prior to discuss this work and answer any questions.
Essential work to increase drinking water supply and improve our electricity network is being carried out from early November for the fast-growing eastern suburbs.
Porirua City Council, Wellington Electricity, Wellington Water and Kāinga Ora are teaming up to carry out essential infrastructure work along two Transmission Gully motorway link roads. To keep disruption to a minimum, we are working together using a ‘dig once’ approach to get both water and electricity upgrades done at the same time.
In stage 1, we’ve temporarily closed Waitangirua Link Road. This closure will allow us to:
- lay cables for improved electricity supply
- lay pipes to increase drinking water supply.
While the road is closed, we’ll also remove wilding pine trees, clear vegetation, resurface the road and install signage for the increased speed limit on the Waitangirua Link Road, which is being raised to 60km/h as part of the Speed Management Plan for Porirua City.
Once the stage 1 work is complete and Waitangirua Link Road is back open, we’ll be closing one lane of Te Ara Kāpehu (Whitby) Link Road for about two months to lay water pipes and power cabling (stage 2). This work will happen in 2025.
The 2.4 km of new drinking water pipes will connect to the new, larger reservoir that is being built at the end of Stemhead Lane in 2025 by Te Rā Nui. The new power cables will enable our city to have a more resilient electricity network and allow future growth.
In 2025 we will be laying electricity ducting and water pipes in the Warspite Avenue/Niagara Street intersection with work starting on 14 January.
This is a part of the Waitangirua Link Road works and will be closed for approximately two months.
What to expect:
Spinnaker Drive slip and road closure updates can be found here: poriruacity.govt.nz/spinnaker