Road closures, road works or temporary restrictions in Porirua City

Keep up to date with any road closures, temporary restrictions, or disruptions within Porirua City.

Current road closures, road works, temporary restrictions, and disruptions in Porirua

Updated on 15 November 2024

There are times when emergency events and largescale improvement projects force the closure or disruptions of roads in Porirua City, sometimes for a number of weeks or longer.

We appreciate this is disruptive for residents and do our best to reopen roads as soon as it is safe to do so.

The following road works, road closures or disruptions are currently active in the city.


Aotea


Camborne

Mo Street from the Lily Close roundabout to the new development will be closed for up to four days between 19 November and 27 November, with three days allowed as a contingency. Gillies Group will be carrying out work to the road and creating a new entry to the development.

Access to the footpath and road will be made available to residents during the road closure between 7am and 5pm, outside these hours everyone will have full access.

We thank road and footpath users for their patience while this work is carried out.

Powerco is doing a gas pipeline upgrade in Grays Road and Mervyn Place between November 2024 and January 2025. Work will be done under Stop / Go traffic control during the hours of 9am and 4pm only. There will also be lane closures so expect some delays at times.

If you have any queries about the pipeline upgrade, please direct your enquiries to Powerco 021 728 919


Cannons Creek

Sewer main construction & water main renewal

Both lanes of Champion St are now open, however the entrance to Bothamley Park remains closed until further notice.

Read more about this project

Water main renewal

The watermain is being renewed on Gloucester St to replace aging infrastructure to reduce leaks and ensure reliable and safe water supply.

Traffic Management:

Traffic Management continues on east Gloucester as Action Civil works to install the principal main. Parking is still available again in the parking bay lane on west Gloucester. Lane closures and detours will be in place around active work zones. Please follow posted signage and use alternate routes where possible.

The car park outside 14 Bedford Court, Te Akapuanga Hall (Porirua Cook Islands Hall) will be closed between midday and 10pm on the following days for the Pacific Night Market:

Friday 13 December


Elsdon

Electricity cabling - October to December 2024
Wellington Electricity is installing an underground electricity cable between 11 Prosser Street and 24 Mohuia Crescent in Elsdon, Porirua. The project involves digging trenches, installing protective pipes, then covering everything up once the cables are in place. The work is being done in stages.

For up-to-date information about what is happening and when, visit the Wellington Electricity project page: https://www.welectricity.co.nz/major-projects/elsdon/

Water main installation - January to December 2024

Wellington Water is working to install a new water main on Titahi Bay Road (near Wi Neera Drive) and along Tangare Drive.

The project is expected to take approximately eleven months to complete. It is being carried out in stages and is a joint effort between Wellington Pipelines and Wellington Water.

Please be aware the work will cause some road and footpath disruptions, with some works carried out at night as required.

We thank road and footpath users, and residents of the area for their patience while this important project is completed.


Kenepuru

Beginning on 20 November, for two nights, Wellington Water will be replacing a sluice valve box at the intersection of Lyttleton Avenue and Kenepuru Drive. The work will be carried out overnight between 7pm to 5am to minimise disruption, and stop/go traffic control will be in place. Your patience is appreciated while this major work is carried out. If you have any questions, please contact Wellington Water on 04 912 4400.


Papakōwhai

A slip in 2022 has resulted in the long-term closure of the walkway between Halladale Road & Kinloch Grove.

The retaining works required will be programmed as priorities and budget allow.

There is currently no timeframe for these works - and the walkway will remain closed until it can be safely reopened.

We recognise this closure will be frustrating for many residents.


Paremata / Mana


Pāuatahanui

Our arborists will be working in Moonshine Road for the week starting Monday 18 November. Traffic management will be in place.

The week beginning 21 October, Downer will be carrying out repairs to the road in the following four approximate locations along Moonshine Road:

  • 1087 – 1160
  • 999 – 1071
  • 930 – 999
  • 815 – 930

Stop/Go traffic management will be in place. We understand roadworks can be disruptive and Downer will endeavour to minimise the impact on the community. We appreciate your co-operation and patience.

Our arborists will be working in Mulhern Road for the week starting Monday 18 November. Traffic management will be in place.

Northpower (on behalf of Wellington Electricity) is replacing a power pole and carrying out maintenance work on other poles on Murphy’s Road, Judgeford.

Work is planned for Tuesday 12 November and could continue until Friday 15 November between the hours of 8am and 4pm.

Pedestrians and resident vehicles will be assisted through the closure by the traffic controllers if required.

Northpower (on behalf of Wellington Electricity) is replacing cross-arms on several electricity poles from 171 Belmont Road, Judgeford.

Work is planned for Tuesday 12 November and could continue until Friday 15 November between the hours of 8am and 4pm.

Pedestrians and resident vehicles will be assisted through the closure by the traffic controllers if required.


Plimmerton


Pukerua Bay


Rānui

Sewer main renewal - 24 July to 15 November

The entrance to Mepham Place is now open but the work is on hold. Installation of the last manhole has been deferred and the website will be updated when we have a firm date for completion.

Windley Street will be closed from Wednesday 24 July to Friday 15 November at the intersection of Windley Street and Champion Street.

There will be a full road closure of Windley Street, between Thompson Grove and Champion Street. One lane will remain open on Champion Street, with traffic managed under a Stop Go operation. This area will be closed continuously for nine (9) weeks, including a two (2) week contingency buffer if required.

GP Friel on behalf of Kainga Ora, will be carrying out a wastewater renewal project during this road closure. A significant trench depth is required for the work, which requires large construction machinery. As such, most of the available road and footpath space is required

Residents and the business owner have been notified as part of the Mana Whenua Partnerships team’s notification process within Te Aranga Alliance. Contractors will be installing signs at the end of this closure to indicate that the business remains open and accessible.

Sewer main renewal - 24 July to 15 November

Windley Street will be closed from Wednesday 24 July to Friday 15 November at the intersection of Windley Street and Champion Street. GP Friel on behalf of Kāinga Ora, will be carrying out a wastewater renewal project during this road closure.

There will be a full road closure of Windley Street, between Thompson Grove and Champion Street. One lane will remain open on Champion Street, with traffic managed under a Stop Go operation.

The businesses remains open and accessible.


Titahi Bay

Starting from Monday 4 November, Downer, our maintenance contractor will be carrying out a sump repair. Stop/Go traffic management will be in place.

We understand this work can be disruptive and Downer will endeavour to minimise the impact on the community. We appreciate your co-operation and patience.

From mid-week, road repairs will be carried out by Downer, our maintenance contractor, between 9am – 5pm (week beginning 4 November). Stop/Go traffic management will be in place.

We understand roadworks can be disruptive and Downer will endeavour to minimise the impact on the community. We appreciate your co-operation and patience.

A contractor for Wellington Electricity is carrying out work for a cable upgrade from Monday 4 November for approximately 8 weeks. Stop/Go traffic management and/or road shoulder closures will be in place. The footpath will remain open to pedestrians.

We understand roadworks can be disruptive and Wellington Electricity’s contractor will endeavour to minimise the impact on the community. We appreciate your co-operation and patience.

Water main installation - January to December 2024

Wellington Water is installing a new water main on Titahi Bay Rd (near Wi Neera Drive) and Tangare Drive, Elsdon.

The project was expected to take approximately eleven months to complete and is a joint effort between Wellington Pipelines and Wellington Water. It is now nearing completion and final tests and reinstatements will follow in the next month or so.

Please be aware the work will cause some road and footpath disruptions.

We thank road and footpath users and residents of the area for their patience while this important project is completed.


Waitangirua


Whitby

Spinnaker Drive slip and road closure updates can be found here: poriruacity.govt.nz/spinnaker


State Highway disruptions and closures

For road closures and road works on state highways in Porirua City please follow www.nzta.govt.nz/wellington-maintenance for updates


Traffic advice

  • Well-maintained roads are an important part of keeping people safe. While we aim to do this work with as little disruption as possible, we know that roadworks can be inconvenient. 
  • Please drive carefully through work sites and stick to the temporary speed limits. 
  • If you’re driving around the Wellington region, roadworks on the state highway network may affect your travel plans.
  • Please contact us on (04) 237 5089, email [email protected], or use the Antenno app to report any concerns in your street so we can respond.