Status:
Item | Date |
---|---|
Submissions for RC8436 – LU0125/21 (short-term operations) closed | May 2021 |
Submissions for RC7695 - LU0055/20 (long-term operations) closed | January 2022 |
The decision report was released by the Independent Hearing Panel | 17 October 2022 |
An appeal was made to the Environment Court by a submitter | 14 November 2022 |
The decision is therefore subject to approval by the Environment Court.
Willowbank Quarry Hearing Notice
Willowbank Quarry Resource Consent Applications Joint Hearing Schedule
If you have any questions or concerns relating to the hearing, please contact the Hearing Administrator [email protected]
Resource Management Act 1991
Notification of Application for a Resource Consent under Section 95A(3) (a)
Name of applicant: Willowbank Trustee Limited
Council reference: RC8436 – LU0125/21
An independent Panel of Commissioners have been appointed to hear this matter - David McMahon, of Resource Management Group Ltd (RMG) as Chair.
Please note that the Minutes relate to both applications:
You can find the Application RC7695 - LU0055/20 website page here.
22 July 2022 | Council S42A reports and evidence due |
29 July 2022 | Applicant evidence due |
5 August 2022 | Submitters expert evidence due |
15 August 2022 | Hearing Commences (15, 16, 17, 18 and 19 August 2022) |
Issued by Panel
Issued by Councils
Please refer to the following directions minutes issued by the Commissioner, and the associated responses requested or additional information received:
Minute 1:
Minute 2:
Minute 3:
Minute 4:
Minute 5:
Minute 6:
Minute 7:
Minute 8:
Minute 9:
Minute 10:
Minute 11:
Minute 12:
Minute 13:
Minute 14:
Greater Wellington Regional Council
Porirua City Council
The following documents have been provided which reflect updated information provided by the applicant:
Additional noise and traffic info response - LU012521 RC8436
Ecological response - Willowbank quarry - Avian Community
Feb 2022 - Willowbank responses to pcc transportation
Response to RFI - Landscape and Visual Assessment Housing Inventory (2)
Tranche 1 - Willowbank Quarry - response to RFI - 24 Sept 21
Tranche 2 - Response to RFI - 22 Oct 2021
Updated Air Quality Technical Assessment - September 2021
Updated description of the project 18.07.2022.
Updated Ecological Assessment - July 2022 - Willowbank Quarry Extension_EcIA_r2.1
Updated noise memo - 7 July 2022 (Updated modelling results)
Updated Transport Status v3 12jul22
All expert evidence was filed 22 July 2022
Porirua City Council
Greater Wellington Regional Council
Expert Evidence - GWRC - Nicholas Singers - Wetlands
Expert Evidence - GWRC - Michael Greer - Freshwater Ecology
Expert Evidence - GWRC - Hamish Smith - Flooding
Expert Evidence - GWRC - Gregor McLean - Erosion and Sediment Control
Applicant Evidence - Bram Mulling (Ecology)
Applicant Evidence - Glenn Pope (Construction Water Management)
Applicant Evidence - Wade Robertson (Landscape and Visual)
Applicant Evidence - John Row (Traffic Modelling)
Applicant Evidence - Mathew Noonan (Air Quality)
Applicant Evidence - Nathan Baker (Planning)
Applicant Evidence - Paul Lucich
Applicant Evidence - Paul Nation
Applicant Evidence - Peter Walsh / Updated Evidence - Applicant - Peter Walsh (12 August 2022)
Porirua City Council
Summary Statement - Porirua City Council - Karen Williams - Planning
Summary Statement - Porirua City Council - Simon Button - Landscape
Summary Statement - Porirua City Council - Jamie MacKay - Terrestrial Ecology
Summary Statement - Porirua City Council - Malcolm Hunt - Noise
Summary Statement - Porirua City Council - Sandy Ormiston - Engineering Geology
Summary Statement - Porirua City Council - Harriet Fraser - Transport
Summary Statement - Porirua City Council - Jon Styles - Vibration
Greater Wellington Regional Council
Summary Statement - Greater Wellington Regional Council - Genevieve Walker - Planning
Summary Statement - Greater Wellington Regional Council - Nicholas Singers - Wetland Ecologist
Summary Statement - Greater Wellington Regional Council - Deborah Ryan - Air Quality
Summary Statement - Greater Wellington Regional Council - Gregor McLean - Erosion and Sediment
Summary Statement - Greater Wellington Regional Council - Michael Greer -Freshwater Ecologist
Applicant
Summary Statement - Applicant - Nathan Baker - Planning
Summary Statement - Applicant - Wade Robertson - Landscape and Visual
Summary Statement - Applicant - Bram Mulling - Ecology
Summary Statement - Applicant - Glenn Pope - Erosion and Sediment
Summary Statement - Applicant - Tim Kelly - Transport
Summary Statement - Applicant - Siiri Wilkening - Acoustics
Summary Statement - Applicant - Mathew Noonan - Air quality
Submitters
Summary Statement - Waka Kotahi - Sarah Jenkin - Planning
Willowbank hearing Updated Summary Statement - Sarah Jenkin - Planning (17.8.22)
Summary Statement - Waka Kotahi - Jason Chow - Transport
Willowbank Quarry Updated Summary Statement - Jason Chow - Transport (17.8.22)
Summary Statement - JEPS - Rebecca Stirnemann - Ecology
Tabled letter Guardians of Pauatahanui Inlet and Te Awarua-o-Porirua Catchments and Community Trust Tabled Day 1 (11.8.22)
Day 1 (Monday 15 August 2022)
Day 2 (Tuesday 16 August 2022)
Day 3 (Wednesday 17 August 2022)
Day 4 (Thursday 18 August 2022)
Day 5 (Friday 19 August 2022)
PDF versions:
Word version:
Resource Management Act 1991
Notification of Application for a Resource Consent under Section 95A(3) (a)
Name of applicant: Willowbank Trustee Limited
Council reference: RC8436 – LU0125/21
The applicant proposes: Continued long-term operation of the Willowbank Quarry and expansion of the existing quarry footprint.
This will involve the following broad activities:
Fulton Hogan, as quarry operator, is proposing that the quarry will normally operate from Monday to Friday, between the hours of 6am and 6pm, and on Saturday, between the hours of 6am and 3pm.
The application notes that from time-to-time Fulton Hogan may be required to operate the quarry between 6pm to 10pm to cater for the needs of local projects, which is why hours of operation of 6am to 10pm are being requested. Any blasting activity will only occur between 9am and 6pm.
Resource Consent is required for the proposal as it is not provided for as a Permitted Activity in the Rural Zone in the Porirua City District Plan (the District Plan). The proposal is considered to be a Discretionary Activity pursuant to Rule D4.1.4 of the District Plan.
The application may be inspected at the Porirua City Council, Administration Building, Customer Service Centre (ground floor), Cobham Court, Porirua, between the hours of 9.00am and 5.00pm.
The Applicant has lodged a separate Resource Consent with the Greater Wellington Regional Council, which is also publicly notified. Further details and information relating to this application can be found on the Wellington Regional Council website: haveyoursay.gw.govt.nz/willowbank-quarry
Please contact Ellen Seumanufagai on 04 237 1494 if you have any questions about the application.
Greater Wellington Regional Council Application documents etc below:
Submissions closed 5pm on 11 January 2022
All information provided as part of the submissions process will be publicly available. You can request that certain details are withheld for privacy reasons.